Home › Sales › SO-2606-0042

Sales Order SO-2606-0042

Dashboard
Order Summary
In Production
Customer
Lalitha Jewellery
Design
URVASHI
Units
25
Length
24 in
Weight / Unit
32.00 g
Total Weight
800.00 g
Required By
Jun 21, 2026
Production Planning
Required Gold
879.09 g
Available Gold
-2141.62 g
Required DYE
DYE-M-52/4L
DYE Status
Available After Release
Recommended Machine
15
Machine Status
Running
Production Time
92.5 hr
Earliest Start In
48.0 hr
Expected Completion
Jun 27, 2026, 7:13 AM
Expected Delivery
Jun 28, 2026, 7:13 AM
Confidence
67%
Promise
Not Manufacturable
Gold Allocation
3 melt orders
Required Fine
879.092 g
Allocated
672.550 g
Priority Melted
198.150 g
Remaining
206.542 g
MO-2025-0114
Full
BATCH-2606-0118
249.750 g · Completed
MO-2025-0123
Priority
BATCH-2606-0123
198.150 g · Completed
MO-2025-0126
Standard
BATCH-2606-0126
224.650 g · Completed
Pct allocated: 77%. Priority portions move ahead of standard in shop-floor queues.
Order Promise Result
Not Manufacturable
Expected Start
Jun 23, 2026, 10:43 AM
Expected Completion
Jun 27, 2026, 7:13 AM
Expected Delivery
Jun 28, 2026, 7:13 AM
Confidence
67%
⚠ Promised delivery is 169 hr after required date (Jun 21, 2026).
  • Gold shortage: 3020.71 g (procurement ~48 hr)
  • DYE DYE-M-52/4L releases in 24 hr
  • Recommended machine status: Running (free in 9 hr)
WPI / DYE Configuration
Choose a configured WPI / DYE option (nearest below, matched, nearest above):
Material
Procurement Required
Required Gold879.09 g
Raw Available319.84 g
Reserved2461.46 g
WIP467.62 g
Shortage3020.71 g
DYE
Available After Release
Required DYEDYE-M-52/4L
DYE Number52/4L
Wire Config4-Line
Master StatusMaintenance
Release In24 hr
Machine
Running
Recommended15
TypeAnchor Chain
OperatorVignesh R.
Free In9 hr
Alternates
Consumables Required
ConsumableRequired (g)In Stock (g)Status
Copper (alloy)72.886850.00
OK
Single Solder1.200120.00
OK
Powder Solder2.80095.00
OK